Tarragindi Playground and Building Extension

Tarragindi gets a new playground and new staffroom

Project Details

Location
Tarragindi, QLD
Size
Approx. 160 m²
Timeframe
16 weeks

Building Extension for new staff room

Tarragindi staff had been hanging out for a space that they could make their own and lucky for them when Edge Early Learning took over ownership and decided to upgrade this was a big part of the renovation.

We were required to:

  • Upgrade existing downstairs bathroom

    • Remove existing fixtures and fittings
    • Remove walls
    • Reframe bathroom
    • Line walls
    • Lay vinyl flooring
    • Install new fixtures, windows, and sliding door
    • Paint and tile walls
  • Demolition of the entire play yard & removing all unwanted surface materials, play and shade structures, unwanted gardens and any unwanted soils including waste management

  • Excavate and level the area

  • Construct new block retaining walls under existing building.

  • Build new foundations by inserting pillars for the new building extension

  • Remove the existing exterior wall

  • Electrical Fit out

  • Plumbing fit out

  • Erect steel subfloor structure

  • Install new subfloor framing

  • Demolition of the entire play yard & removing all unwanted surface materials, play and shade structures, unwanted gardens and any unwanted soils including waste management

  • Excavate the existing land

  • Construct new block retaining walls under existing building.

  • Build new foundations by inserting pillars for the new building

  • Remove the existing exterior wall

  • Electrical Fit out

  • Plumbing fit out

  • Erect steel subfloor structure

  • Install new subfloor framing