State School handball court upgrade

Handball court upgrade

Project Details

Location: Robina, QLD

Size: Approx. 36 m²

Timeframe: 1 week

Scope of works

We were tasked to upgrade the current handball court over the school holidays so that the works didn’t interrupt the school.

  • Remove existing turf

  • Level the ground and lay new compacted crusher dust

  • Lay new artificial turf

  • Lay tennis markings

  • Paint existing Brick wall and surrounding pipes

handball court- before photohandball court upgrade

Gallery